3 Aug 2016:
Having considered the comments received, the Consultants’ responses thereto and their revised report, EMA makes the Draft Determination on the LRMC parameters for setting the 2017 and 2018 vesting contract price as set out in Appendix 1 (for the financial parameters) and Appendix 2 (for the technical parameters). Overall, the indicative vesting price for 2017-2018 (assuming the weighted average gas price of S$9.87/GJ for Mar to May 2016) is $122.03/MWh, marginally lower than the current vesting price of $122.33/MWh.
EMA invites comments on the Consultants’ Revised Reports and EMA’s Draft Determination. All comments must be submitted using the format in Appendix 3and in both PDF and Microsoft Word format. Please submit your comments in writing via email to Mr Eugene Lim (eugene_lim@ema.gov.sg) and Mr Lim Yew Hua (lim_yew_hua@ema.gov.sg) no later than 5 pm on 22 Aug 2016.
6 Jul 2016:
The consultation has closed for comments.