Budget & Fees
Under the Market Rules Chapter 2 Section 12.1.3, PSO is required to
publish its finalised budget and fees for 3 consecutive fiscal years. Where
there is under/over recovery at the end of each fiscal year, Chapter 2 Section
12.1.5 of the Market Rules required the PSO to publish the revised expenditure
and revenue requirements and schedule of fees as soon as reasonably
practicable.
The revised expenditure and revenue requirements and schedule of
fees (as at 1 August 2022) are shown below:
| FY 2021/22 |
FY 2022/23 |
FY 2023/24 |
PSO proposed expenditure and revenue requirement for 3-fiscal year period ($'000) |
30,773
|
32,044
|
33,961
|
Previous year's audited adjustments | (5,402) | (2,351) | - |
PSO finalized expenditure and revenue requirement for each FY | 25,371 | 29,693 | 33,961 |
Projected Electricity Sales (GWh) |
50,061*
|
60,108 |
62,500
|
Estimated PSO Fees ($/MWh)** |
0.2534
|
0.2470
|
0.2717
|
Note:
(1)* Actual Electricity Sales figure for previous fiscal years.
(2)**Based on MWh traded (~2 times of projected electricity sales) in the wholesale electricity market. The PSO Fee excludes the estimated PSO Fixed fees (which was introduced in 1st Jul 2018) of $200,000 annually, which will be collected separately.
Back to Top